In January 2021, ŠKODA PRAHA entered into an agreement with ORLEN UNIPETROL to provide all work and services related to the implementation of the project “Pre-project preparation of a new energy plant/source (“Teplárna T600”) project at ORLEN UNIPETROL”. Work on project preparation began immediately after the contract was signed. According to the project schedule, the tender for the supplier of the new plant should be launched in the middle of 2021 and the contract with the general contractor concluded by the end of 2022.

Works provided by ŠP include:

  • The process of preparation and implementation of the EIA
  • Elaboration of documents for the issuance of a new integrated permit
  • Preparation of documentation for joint land and construction permits
  • Preparation of the technical part of the documentation for the tender for the supply of a new energy plant and for a Long Term Service Agreement (LTSA) for gas turbines
  • Cooperation during implementation of a tender for the supply of a new energy plant and for a Long Term Service Agreement for gas turbines
  • Support in negotiations with bidders during the tender procedures for the supply of a new energy plant and for a Long Term Service Agreement for gas turbines
  • Cooperation in negotiations with state administration bodies in obtaining required permits